City of Leduc RCMP

Project Details

DESIGN START June 2018
CONSTRUCTION START Nov 2019
COMPLETION in construction
ORIGINAL BUDGET $ 18.2M
AREA 5,987 m2

SK-ACI began work with the City of Leduc and EllisDon Construction Ser-vices
Inc. on the existing detachment. A 3D point model was generated with
the latest scanning technology to help location all the walls and ceilings, as
well as services and structures in the plenum spaces, forming a base for the
Revit model. With the coordination with the general contractor, the owner/
users, and consultants the model was manipulated to generate information
to help in the designing of the spaces and the additions.

Based on the need to keep the detachment open while construction was un-derway,
the project was split into phases. The additions were designed and
scheduled to be completed frst to allow for the users to relocate into these
new spaces while the renovations of the existing detachment take place.

Building construction Phase 1 includes additions to the northwest and east
sides of the building, a three storey building and out buildings. Building con-struction
Phase 2 to 5 includes demolition of existing garage bays to extend
building to the north; removing existing interior walls, millwork and fnishes
to construct new spaces within the building; removal of exterior wall fnish-es
and replacing with new building envelope and cladding; additional front
entrance with canopy and exterior glass enclosure.

Currently the foundations for the additions are being constructed as the
frst phase and will continue for the next year. We are continuing with the
next phases and the renovation packages will be tendered in the spring